Kennesaw plans to demolish the former downtown public library and replace it with a public parking lot at 2250 Lewis Street. The roughly half-acre property is near North Main Street, and plans call for 48 new parking spaces.
The lot will add downtown parking and help support redevelopment of the Collier Building at 2881 North Main Street, across Lewis Street. That building is being converted into Kennesaw Tap & Market, and a portion of the spaces in the new lot will support their new home in the J. G. Lewis Building (Collier Building), which has no parking of its own.
The property’s history reaches back to a much smaller downtown library operation. In 1963, Kennesaw’s first public library opened in a converted garage at the old City Hall on the southeast corner of Cherokee and Main streets.
The Lewis Street branch opened in 1967 as part of a Cobb County library construction program financed through a bond issue. It was one of seven Cobb branches that opened that year. The library expanded in size to 5,099-square-feet in 1989 and later had $25,000 in renovations done in 2003.
The Kennesaw and Acworth branches closed on July 13, 2019, as Cobb County prepared to consolidate them into the North Cobb Regional Library. The new library opened that September at 3535 Old 41 Hwy NW in Kennesaw, across from North Cobb High School and about 2.5 miles from the old Lewis Street location.
The consolidation moved library service into a much larger 25,000-square-foot facility with a children’s room, teen space, computer training lab, makerspace, meeting rooms, and study rooms. Library service continued in the larger regional building, while the Lewis Street property remained under Cobb County ownership.
In January 2025, Kennesaw City Manager Jeff Drobney announced that the City of Kennesaw had purchased the former library property for $470,000, down from $550,000 previously asked for by Cobb County.
The building’s condition helped determine its next use. At an April 17, 2025 meeting, Planning and Zoning Administrator Chanelle Campbell said the city found flooding, a collapsed roof, and a broken window above the entrance. She told commissioners that other uses had been considered, but the building’s deterioration left no viable alternative to the parking proposal.
An updated site and landscaping plan was released on August 21, 2026, showing additional landscaping, revised access, and sidewalk connections. The plans also call for a contractor under contract by the end of 2026 and construction beginning in early 2027. Like all government work, that timetable remains tentative.